Project Description
Client: City of Dover, Delaware
Year Completed: 2017
Engineer: Pennoni Associates, Inc.
This project for the City of Dover, DE involved the rehabilitation and replacement of an existing pump station. The challenge on this project was bypassing the flow of the pump station from three separate influent pipes. M2 Construction worked with the City of Dover to coordinate and install a temporary manhole to set up the bypass functions from in order to alleviate disruption in service to the community. With the bypass manhole installed, M2 started with selective demolition and proceeded to the lining of the existing wet well. After the lining was complete the new pump station was installed and tested. The pump station went online in December 2017 and then the bypass manhole was removed so that the property could be restored to its original state.