Project Description

Client:  Town of Rock Hall, Maryland
Year Completed:   2015
Engineer:  McCrone, Inc., Annapolis, MD

This project consisted of construction and installation of a new clarifier and related upgrades to the Rock Hall Water Treatment Plant. The scope of work included concrete construction of a new 40′ diameter clarifier, installation of the clarifier, aerator and chemical feed equipment. M2 Construction reconfigured the existing building through demolition and reconstruction to add a new chemical feed room and new electrical room. The work included installation and startup of all the equipment, generator, control panel and all associated piping. Special care was taken on this project to properly disinfect the equipment and piping before water was fed to the town system.